83 percent construction of Postal Highway completes in one and half decades

KATHMANDU, Jan 13: Around one and a half decade into construction, 83 percent work on the Postal Highway has been completed. It will take around three more years for the national pride project to complete, it has been said.
By Republica

KATHMANDU, Jan 13: Around one and a half decade into construction, 83 percent work on the Postal Highway has been completed. It will take around three more years for the national pride project to complete, it has been said. 


Under the project considered to be a base for the prosperity of the Terai Madhesh, construction of 910 kilometers of road and 115 bridges have been completed. 


The COVID-19 pandemic, disputes related to the project location and the border blockade are blamed for the delay, said Dharmendra Kumar Jha, chief of the Postal Highway Directorate. The construction of around 250 kilometers of road has yet to be contracted, and work on around 500 kilometers is underway, said the directorate. 


Related story

Postal Highway achieves completion target of 70 percent


Negligence of the contractors in some cases is blamed for the delay, said Jha, adding that in some other cases, the contract was extended from time to time. 


Chief Jha said although there was an arrangement to extend the deadline in the past, now construction companies could be fined for their failure to complete the works within the deadline. 


Now, around 500 km of road is under construction under the project. According to the directorate, the contract would be canceled if works are not carried out as per the schedule. 


According to the project, a target has been set to construct 27 bridges and to blacktop 160 km of road in the current fiscal year. 


The latest deadline has been extended till current fiscal year 2022/23. Chief Jha said COVID-19 has affected this project like many other development projects.


 

See more on: Terai_Madhesh
Related Stories
ECONOMY

Mid-hill Highway makes 64 percent progress in one...

ECONOMY

Postal Highway to miss yet another deadline as onl...

SOCIETY

Four decades on, Postal Highway still incomplete

ECONOMY

Half of the construction work of Tanahun hydropowe...

ECONOMY

Construction of Pokhara Bus Park remains incomplet...

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights