Bridge over Karnali river ready after nine years

MANMA, Nov 11: Construction of a concrete bridge over the Karnali river at Naraharinath Rural Municipality-1 in Kalikot district linking Hilsa in Humla district has been completed after nine years.
By RSS

MANMA, Nov 11: Construction of a concrete bridge over the Karnali river at Naraharinath Rural Municipality-1 in Kalikot district linking Hilsa in Humla district has been completed after nine years. 


The bridge was supposed to be completed within one year after construction agreements in 2067 BS. But negligence of the contractor and other various reasons are blamed for the delay. Kankai Nepal Pragati JV won around Rs 140 million contracts to construct the bridge. The bridge will come into operation within one month, said the owner of the contracting company, Dipak Mainali. "All construction work has been completed," he said. 


Related story

Pappu Construction fails to build bridge, govt breaks contract


Without a bridge, people in the locality were forced to cross the river through a risky means of ferry. They also transport vehicles across the river through this means. 


With the construction of the bridge under the Karnali corridor, transportation service will now be easier to people of five villages of Kakikot and Bajura districts each and people of Mugu and Humla districts, said Raskot Municipality Mayor Kashi Chandra Baral.


 

Related Stories
SOCIETY

Bridge construction still continues after four yea...

SOCIETY

Villagers await completion of Likhu bridge after f...

ECONOMY

Imja River bridge still uncertain

SOCIETY

18 years on, motorable bridge in Jhulaghat still a...

SOCIETY

Karnali likely to enter Bardiya settlements as emb...

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights