Contractors selected for five packages of Koshi Corridor road project

PANCHTHAR, Feb 5: Construction work on Koshi Corridor, which connects eastern hilly districts with the tarai plains, is beginning soon.
The track of Koshi Corridor road at Panchami of Panchtar district. Photo: Giriraj Baskota/Republica
By Giriraj Baskota

PANCHTHAR, Feb 5: Construction work on Koshi Corridor, which connects eastern hilly districts with the tarai plains, is beginning soon. 


The process of awarding contract for a double-lane road between Ganesh Chowk of Panchthar and Chatara of Sunsari is in the final leg, according to Pushpalal Mid-Hills Highway Project Office which is implementing the project. 


According to the office, contractor for five out of seven packages of the road project has been selected. The office has already notified the selected contractors about the decision, asking them to come and sign project agreement. Similarly, it is in the process of selecting contractors for the remaining two packages.


Related story

Progress on Koshi Corridor excites local entrepreneurs


Though the estimated cost of the project is Rs 7 billion, it is expected to come down to around Rs 5 billion as contractors have quoted lower price to get the contract.


Koshi Corridor is considered the shortest routes for people of Panchthar, Taplejung, Terhathum and Dhankuta to go to the capital city or markets in the southern plains of the country. According to the contract provisions, the project has to be completed within 30 months.


The road will be built along the banks of Koshi and Tamor rivers. From Chatara, the road heads northward to Mulghat before moving along the banks of Tamor River till Subhang Khola; and then meets Mechi Highway. From Mechi Highway it meets Mid-Hills Highway at Ganesh Chowk of Panchthar.


“The existing road is too long and winding as we had a compulsion to take the road through towns, villages and settlements. This new road, which moves along the riverbanks, will be shorter,” Kuber Nepali, chief of North-South Highway Division Office, said. “It will be the shortest road for people of eastern hills to travel to Dharan, Biratnagar and Itahari as well as Kathmandu.” He further added that graveled road will be ready within two years.


The section between Mulghat and Subhang Khola falls under Koshi Corridor which is being to develop a trade route between eastern Nepal and Tibet Autonomous Region of China.


The Chatara-Mulghat section of the road is 35 kilometers; while the section between Mulghat and Ganesh Chowk is 112 kilometers, according to the project office.


According to the contract document, the contractor will have to hand over the graveled road ready for blacktopping, to the project office. The road will have five motorable bridges.


As the project office has allocated substantial budget for the project, locals are hopeful that the project will be completed within the stipulated time. Once the road is built, Kathmandu will be only around 450 kilometers away from the eastern hilly districts.

See more on: packages
Related Stories
ECONOMY

Gorkha-Barpak road awaits blacktopping

ECONOMY

Contractors face Rs 90 million fine for missing de...

ECONOMY

Road-widening and graveling of Deurali-Pathivara s...

SOCIETY

Rs 112m paid for 11 km Valley roads but no work do...

NEPAL

Contractors of Narayangadh-Muglin road project fin...

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights