Dearth of technicians in Sindhupalchowk affects reconstruction

SINDHUPALCHOWK, Sept 11: “The technicians do not want to stay at all in the village”, says Dr Yuvaraj Poudel, chief of the district coordination committee of the Department of Urban Development and Building Construction. “They come, work for some days and then quit,” he adds.
By DHRUBA DANGAL

SINDHUPALCHOWK, Sept 11: “The technicians do not want to stay at all in the village”, says Dr Yuvaraj Poudel, chief of the district coordination committee of the Department of Urban Development and Building Construction. “They come, work for some days and then quit,” he adds. 


According to Poudel, the entire reconstruction work has been badly affected due to ‘irresponsible attitude’ of the technicians. After working for some time, many are resigning, he said. 


There is lack of 94 such technicians in the district of late, Poudel claimed. They had come and worked for some days but left, he states. 


Related story

Quake-devastated Tatopani bazaar crying for reconstruction


When there is dearth of technicians in village, quick victims cannot get enough help. This often lands them into trouble. 


“The technicians need to sit and discuss house construction procedures and requirements with the villagers and also inspect the construction process. In lack of technicians, people get confused. If they try to use their own mind, they sometimes end up building house in a wrong way which consequently can deprive them of further grant,” Poudel explained. 


Without the required number of technicians, government cannot gather progress report of reconstruction works either. This directly affects reconstruction works. 


“Many quake victims have been deprived of second and third phase of house grant just because they have not been able to produce the required progress document of their houses. This is a very sorry state,” he said. 


The reconstruction authority had created 306 quotas for technicians in Sindhupalchowk, one of the most quake hit districts. This included 165 engineers, 73 sub engineer and 68 assistant sub engineers. According to Poudel, there are only 100 engineers, 55 sub engineer and 57 assistant sub engineers working now. 


“Others have resigned and gone elsewhere,” said Poudel. “While resigning most of them said that they were not happy with the working and living environment here,” he added. 


Meanwhile, an engineer who recently resigned stated that they are leaving also because of security reasons. “Even the people like local representatives give us pressure to certify sub standard house. If we refuse to follow their instructions, they threaten us,” he said. “It is not easy to work in such an environment,” he added.     

Related Stories
SOCIETY

More than 81,000 houses reconstructed in Sindhupal...

SOCIETY

21 govt offices that had collapsed in 2015 quake r...

SOCIETY

Snowfall affects normal life in Helambu ( with pho...

SOCIETY

Lack of budget to demolish old buildings affects r...

SOCIETY

Reconstructed office buildings of five govt office...

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights