Dismal progress in Saljhandi-Sandhikharka-Dhorpatan road project

ARGHAKHANCHI, Feb 19: Even though the construction of the Saljhandi-Sandhikharka-Dhorpatan road started a decade ago, the project has seen very dismal progress as only a five-kilometer stretch of the road has been blacktopped till date.
A blacktopped section of the Saljhandi-Sandhikharka-Dhorpatan road. Photo: Laxman Ghimire
By Laxman Ghimire

Only a 10-kilometer stretch of the road has been blacktopped so far


ARGHAKHANCHI, Feb 19: Even though the construction of the Saljhandi-Sandhikharka-Dhorpatan road started a decade ago, the project has seen very dismal progress as only a five-kilometer stretch of the road has been blacktopped till date.


As there has been no significant progress, the project is preparing to scrap the contract with the construction company, said an official of the project.  


The contract of the 196.2-kilomter road stretch was handed to Biti Jaya Baba JV Swoyambu in 2013. As per the contract, the road should have been blacktopped within four years. But, there has been no progress after December, 2014.


Related story

Division Road Office in Bhaktapur decides to terminate contract...


“Till date, only a five-kilometer road stretch has been blacktopped. We had requested the contractor to continue the work. But the company was reluctant in resuming construction of the project,” said Jay Lal Marasini, chief of the project, adding that the project is preparing to scrap the contract with the construction company.


In the meantime, one of the representatives of the company was arrested by police from the District Administration Office (DAO), Arghakhanchi, almost two years ago. The representative was kept in custody for two days. Even though the representative was released on a condition to resume the work at the earliest, the project has seen almost no progress.


The road project is an alternative to the Tansen-Siddhababa road section. After the completion of the project, residents of Arghakhanchi will reach Butwal in two hours.


Of the 196.2-kilometer road, 10-kilomter is blacktopped; 56-kilometer is graveled, while the remaining 100-kilometer is off-road. Of the 10-kilometer completed road, a five-kilometer stretch was blacktopped before the contract was awarded to Biti Jaya Baba JV Swoyambu.


Till date, a total of Rs 1.50 billion has been spent for the project including the preparation of the detailed project report (DPR). As per the DPR, the estimated cost of the project is Rs 8 billion.


The completion of the project is expected to play an important role in tourism development of the region.


According to Ramji Prasad Ghimire, a member of the provincial assembly, the project will promote the tourist and religious destinations of the region. “We have been taking initiatives for the project work to resume at the earliest,” Ghimire said.


Likewise, Kamal Prasad Bhusal, mayor of Sandhikharka Municipality, said that the municipality is also taking initiatives for the resumption of the project. 


Mayor Bhusal further added that the completion of the project will promote tourism in the region.

Related Stories
SOCIETY

Mid-Hill Lokmarga Highway faces contractor delays

ECONOMY

No plan yet for spending Rs 10 b allocation

SOCIETY

Five years on, just 26% expansion work completed i...

SOCIETY

Melamchi pipe laying work creates traffic snarls i...

SOCIETY

Contract awarded a year ago, work yet to start

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights