MCC Board rejects speculative schedule for transmission line project

KATHMANDU, Dec 4: The Board of Directors meeting of the Millennium Challenge Account Nepal (MCA) has directed a reassessment of the proposed timeline for the procurement and construction of the transmission line project.
By Republica

KATHMANDU, Dec 4: The Board of Directors meeting of the Millennium Challenge Account Nepal (MCA) has directed a reassessment of the proposed timeline for the procurement and construction of the transmission line project.


Chief Executive Officer Khadga Bahadur Bista said that the procurement plan and schedule have been made so that it will take more than one and a half years to start the construction of the transmission line project.


Related story

220 kV Marsyangdi Corridor Transmission Line Project achieves o...


However, during the board meeting, concerns were raised about what was perceived as a lack of urgency and commitment from the MCA management towards the project. The board instructed the management to revise the proposed schedule and submit a new proposal.


During the meeting, board members also issued a warning to the management, stating the importance of avoiding a lax procurement plan and work schedule that could potentially jeopardize the entire project.


 


 


 

Related Stories
ECONOMY

132 KV substation at Unaychaur in Gulmi nearing co...

ECONOMY

Taplejung emerges as hydropower hub with multiple...

SOCIETY

Trishuli 3B Hub Station comes into operation

ECONOMY

Delay in construction of ‘Chilime Hub' results in...

ECONOMY

Cosmic Electrical completes 220 kV transmission li...

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights