Tunnel of Mistrikhola hydropower project completes

MYAGDI, May 12: The construction of a 2,270 metres long tunnel of the Mistrikhola Hydroelectricity Project has been completed. The project is located at Narchyang of Annapurna rural municipality-4 in Myagdi district.
By Republica

MYAGDI, May 12: The construction of a 2,270 metres long tunnel of the Mistrikhola Hydroelectricity Project has been completed. The project is located at Narchyang of Annapurna rural municipality-4 in Myagdi district.


The 42-Megawatts-capacity project is being constructed by Robust Energy Pvt Ltd. Works on construction of the tunnel had started on June 13, 2016.


Related story

Super Dordi ‘B’ Project completes tunneling of 5.1 km passage,...


The tunnel is 926 metres from the dam site and 1,344.5 metres from the powerhouse outlet, said the project engineer Diwakar Khadka. According to him, 80 per cent of the construction of the dam and the powerhouse and installation of penstock pipe of the project has been completed. A 23 metres high dam has been constructed on the confluence of the Nilgiri and Ghalemdikhola streams.


Similarly, the project has constructed a six kilometers road from Narchyangbesi up to the dam site. It has also constructed three Bailey bridges.


The project is estimated to cost Rs 5.64 billion and it is being built through domestic investment. It is stated that the project was delayed nine years as the Nepal Electricity Authority (NEA) lingered in the construction of the 220-KV Kaligandaki electricity transmission line and the Dana sub-station.


Mistrikhola project is the largest of such projects constructed so far or which are under construction in Myagdi district.

See more on: Mistrikhola
Related Stories
ECONOMY

Main tunnel of Rahughat Hydropower Project achieve...

ECONOMY

Main tunnel of 900MW Arun III Hydropower Project a...

ECONOMY

HRT tunnel of Kabeli-3 Hydropower Project complete...

ECONOMY

140 MW Tanahun Hydropower sees breakthrough of hea...

ECONOMY

Breakthrough achieved in Kaveli-3 Hydropower Proje...

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights