CHAUTARA, Feb 8: The Upper Bhotekoshi Hydropower Project that suffered badly from the natural disasters and faced five years of closure has now grasped the momentum in its reconstruction bids.
By No Author

CHAUTARA, Feb 8: The Upper Bhotekoshi Hydropower Project that suffered badly from the natural disasters and faced five years of closure has now grasped the momentum in its reconstruction bids. 


Authorities said that around 40 percent of the reconstruction works of the project have been completed so far. 

The project with 45 megawatt of capacity located at Bhotekoshi Rural Municipality in Sindhupalchowk district and developed from the private sector remained closed for almost five years following the Jure landslide of 2014, Gorkha Earthquake of 2015 and heavy flood in the river occurred in 2016. The reconstruction works of the project were started from the last fiscal year. 


Related story

Local Advisory Council submit memorandum to PM Oli to speed up...


Executive Director Bikram Sthapit said that China's Sino Hydro is carrying out the reconstruction works with the contract agreement in Rs 7 billion targeting to complete the project by 2019. 

 


RSS

Related Stories
ECONOMY

Government expresses commitment to expedite constr...

ECONOMY

Rahughat Hydel Project Sees 60 Percent Constructio...

ECONOMY

Funds being secured to develop Upper Arun Hydel

ECONOMY

Upper Trishuli 3B Hydropower Project construction...

ECONOMY

Madhya Bhotekoshi Hydropower Project gets new dead...

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights