header banner
ECONOMY

Nagdhunga-Naubise tunnel construction sees 27 percent work progress

KATHMANDU, Jan 6: Around 27 percent construction work of Nagdhunga-Naubise tunnel road has been completed.
By Republica

KATHMANDU, Jan 6: Around 27 percent construction work of Nagdhunga-Naubise tunnel road has been completed.


According to Nagdhunga Tunnel Construction Project, it has spent 37 percent of the allocated budget. As of now, a main tunnel of length 736 meter has been constructed. 


Related story

Rahughat Hydel Project Sees 60 Percent Construction Progress in...


Out of the 2,688 meter long tunnel, 372 m has been dug in the eastern side and 364 m has been dug in the west. Similarly, of the evacuation tunnel of 2,557 m, the project has completed its work on the stretch of 1,276 m.


Likewise, construction of two underpasses, four box culverts and two bridges have been constructed. A total of 73.5 percent construction of the access road has been completed. The project is looking to acquire land necessary for construction of a flyover.        


The project is being developed with a total investment of Rs 22 billion. The Japanese government is providing Rs 16 billion in loan assistance while the government is investing the remaining Rs 6 billion.

See more on: tunnel_road
Related Stories
ECONOMY

Kathmandu-Terai Fast Track project sees 26.14 perc...

ECONOMY

Construction of Arun-III Hydro project sees almost...

SOCIETY

Bridge construction over Seti River sees only 20 p...

Editorial

Address locals’ demands to speed up Nagadhunga tun...

ECONOMY

Half of the construction work of Tanahun hydropowe...

Trending

Top Videos

Bold Preety willing to fight for her musical career

Awareness among people on heart diseases has improved in Nepal’

Print still remains the numbers of one platform

Bringing home a gold medal is on my bucket

What is Nepal's roadmap to sage child rights